The grid connection
StarCharge has connected a 1 GW/4 GWh battery energy storage system in Xilin Gol League, Inner Mongolia, to the grid, the company said. StarCharge described the installation as the world's largest single-site grid-forming standalone BESS. It has run stably for three months since the connection, according to the company.
The numbers
The project represents investment of about RMB 3 billion, or roughly US$420 million, and covers 28 hectares. It uses 800 of StarCharge's own 5 MWh battery cabinets, giving a four-hour system 4 GWh of capacity. StarCharge said the station is designed to deliver about 1 TWh of green electricity annually.
What grid-forming does
The station uses lithium iron phosphate chemistry in a grid-forming configuration, which StarCharge said sets voltage and frequency itself rather than following the grid, provides active frequency and voltage regulation, operates in island mode and responds quickly to grid faults. The company said the design is meant to smooth the intermittency and volatility of renewable generation and to support frequency and voltage stability. A full-stack intelligent control system coordinates the storage clusters and manages charging and discharging to balance safety, cost and flexibility.
Construction and purpose
StarCharge said it completed civil works on schedule and commissioned the step-up substation and storage equipment alongside central state-owned enterprise partners, working through the region's climate and construction conditions. The project is designed to supply about 1 TWh a year to Sonid Left Banner and surrounding areas, and is expected to support local industrial output and the development of power equipment manufacturing and operations and maintenance services. StarCharge said the connection is a milestone for its storage business and that it will continue to invest in storage technology and large-scale deployment.